Sample project with illustrative data.

Hunter Data Center Project

Progress & payments

5 packages · updated Oct 15, 2026

Package
Verified complete
61.9%5.2% behind target
1,777 of 2,870 assetsTarget today 67.1%
Forecast finish
Jan 2, 2027
12 days after PC (Dec 21, 2026)
Set by the slowest package: SC-04 BMS & controls
Critical path
259 / 411
152 still open
Blocked
25
Assets with an open blocking record, such as an NCR
Claimable now
$620K
of $4.8M in milestones

Verified progress · Hunter Data Center Project

Assets with evidence linked and nothing blocking, week by week. Rebuilt from the evidence audit trail, back to day one.

VerifiedTargetForecast at the 4-week rateScope (asset register)PC date◆ Milestone due date

Target is the sum of every package’s straight line from its first asset upload to its PC date.

Show the numbers
WeekVerifiedTargetScopeCritical path openBlocked
Today (Oct 15)1,7771,9252,87015225
Oct 121,7061,8662,87016819
Oct 51,5601,7422,87018411
Sep 281,4111,6192,8702108
Sep 211,2101,4952,8702301
Sep 141,0211,3722,8702611
Sep 78671,2322,8032802
Aug 317401,1052,7812982
Aug 245059862,7803352
Aug 173228412,7173523
Aug 102467242,7163703
Aug 31806082,1573181
Jul 271395072,1013172
Jul 201014211,8112633
Jul 13763501,8102661
Jul 6422621,7152601
Jun 29251951,7142621
Jun 22111281,2851700
Jun 154801,0811510
Jun 82401,0801510
Jun 100100

Critical path and blocking

Open critical-path assets have to reach zero by PC. The dashed line is the burn-down needed from today.

Critical path openBlocked assetsNeeded burn-down

Assets verified per week

Speeding up or stalling, against the rate needed to make PC.

Verified that week4-week average: 167/wkNeeded to make PC: 115/wk

Where it's behind

Verified against today’s target, most behind first. The dark tick marks the target.

PackageVerifiedProgress vs target%Gap
SC-04 BMS & controls8 blocked248 / 62839.5%−12.9%
SC-02 Mechanical & HVAC9 blocked303 / 48662.3%−12.6%
SC-01 HV & LV electrical6 blocked831 / 1,24067.0%−5.1%
SC-03 Fire protection2 blocked212 / 31267.9%+2.2%
SC-05 Hydraulics183 / 20489.7%+25.0%

61.9% verified as of Oct 15, 2026. Blocking status uses each package's current label settings.