Sample project with illustrative data.

Hunter Data Center Project

Progress & payments

5 packages · updated Oct 24, 2026

Package
Verified complete
63.4%4.7% behind target
1,820 of 2,870 assetsTarget today 68.1%
Forecast finish
Jan 9, 2027
13 days after PC (Dec 28, 2026)
Set by the slowest package: SC-04 BMS & controls
Critical path
263 / 411
148 still open
Blocked
25
Assets with an open blocking record, such as an NCR
Claimable now
$620K
of $4.8M in milestones

Verified progress · Hunter Data Center Project

Assets with evidence linked and nothing blocking, week by week. Rebuilt from the evidence audit trail, back to day one.

VerifiedTargetForecast at the 4-week rateScope (asset register)PC date◆ Milestone due date

Target is the sum of every package’s straight line from its first asset upload to its PC date.

Show the numbers
WeekVerifiedTargetScopeCritical path openBlocked
Today (Oct 24)1,8201,9552,87014825
Oct 191,7061,8662,87016815
Oct 121,5601,7422,87018410
Oct 51,4121,6192,8702105
Sep 281,2101,4952,8702301
Sep 211,0211,3722,8702611
Sep 148671,2322,8032802
Sep 77401,1052,7812982
Aug 315059862,7803352
Aug 243228412,7173523
Aug 172467242,7163703
Aug 101806082,1573181
Aug 31395072,1013172
Jul 271014211,8112633
Jul 20763501,8102661
Jul 13422621,7152601
Jul 6251951,7142621
Jun 29111281,2851700
Jun 224801,0811510
Jun 152401,0801510
Jun 800100

Critical path and blocking

Open critical-path assets have to reach zero by PC. The dashed line is the burn-down needed from today.

Critical path openBlocked assetsNeeded burn-down

Assets verified per week

Speeding up or stalling, against the rate needed to make PC.

Verified that week4-week average: 165/wkNeeded to make PC: 113/wk

Where it's behind

Verified against today’s target, most behind first. The dark tick marks the target.

PackageVerifiedProgress vs target%Gap
SC-04 BMS & controls8 blocked256 / 62840.8%−12.9%
SC-02 Mechanical & HVAC9 blocked316 / 48665.0%−11.0%
SC-01 HV & LV electrical6 blocked842 / 1,24067.9%−5.2%
SC-03 Fire protection2 blocked221 / 31270.8%+3.8%
SC-05 Hydraulics185 / 20490.7%+25.0%

63.4% verified as of Oct 24, 2026. Blocking status uses each package's current label settings.

Field app

The same sample project, on site.

The Holdpoint iPhone app works from the packages saved on the phone, with or without signal. Everything recorded on site syncs back to the project.

  1. Your packages screen in the Holdpoint field app

    1Your packages

  2. Package, offline screen in the Holdpoint field app

    2Package, offline

  3. Scan a tag screen in the Holdpoint field app

    3Scan a tag

  4. Check sheet screen in the Holdpoint field app

    4Check sheet

  5. Sign off screen in the Holdpoint field app

    5Sign off

  6. Photo to ITR screen in the Holdpoint field app

    6Photo to ITR

  7. Sync queue screen in the Holdpoint field app

    7Sync queue